Dog Park Update and Construction Schedule

dgpk-0317092

Construction workers continue to make progress at the new dog park site. Random dogs from around the neighborhood have been seen loitering around the site, marking their territory in anticipation of the opening. Owners can’t wait as well.

Many residents have asked us about the expected completion date for the park. Below is a schedule that we received from the Redevelopment Agency that outlines the schedule.

Dog Park Schedule Highlights:
Block wall – underway
Tree delivery/installation – begins 4/7/09
Hardscape – begins 4/13/09
Fence Installation – begins 4/27/09
Deck work – begins on 4/28/09
Overhead benches – begins 5/1/09
Landscaping installation – begins on 5/13/09

Construction completed: June 13, 2009

Our dogs will be nipping at their heels to try and ensure they stay on schedule. More to come as we keep you updated on progress.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.